LIST OF ATTEMPTED QUESTIONS AND ANSWERS
 True/False
  Question 
When shop floor scheduling problem larger than 3 machines arise the analytical solution procedures leading to optimality are complex and difficult.
  Correct Answer 
True
  Your Answer 
True
 Multiple Choice Multiple Answer
  Question 
Total lead time is the summation of following factors :-
  Correct Answer 
Queue and transit time , Manufacturing time , Order preparation time
  Your Answer 
Manufacturing time , Delay time , Queue and transit time
 Select The Blank
  Question 
Labour efficiency depends upon ________
  Correct Answer 
Training and experience
  Your Answer 
Training and experience
 Select The Blank
  Question 
The LOB technique is made more accurate and fast by using ________.
  Correct Answer 
Computers
  Your Answer 
Log-tables
 Select The Blank
  Question 
Process plan is the process of establishing the ________ and most economical path that each part is to follow from raw material stage to finished product stage.
  Correct Answer 
Shortest
  Your Answer 
Optimum
 Select The Blank
  Question 
________reflects impact of money tied up in inventory.
  Correct Answer 
Inventory turnover
  Your Answer 
Inventory turnover
 Multiple Choice Multiple Answer
  Question 
The check list approach comprises of following parameters :-
  Correct Answer 
Each department head concerned with efficiency of PPC function is given a set of questions to be answered. , The department head has to answer in "Yes/no" format only , Each "Yes" answer gives one negative score
  Your Answer 
Each department head concerned with efficiency of PPC function is given a set of questions to be answered. , The department head has to answer in "Yes/no" format only , Each "Yes" answer gives one negative score
 Multiple Choice Single Answer
  Question 
In ABC analysis, the classification is based on :-
  Correct Answer 
Cumulative cost
  Your Answer 
Carrying cost
 Multiple Choice Single Answer
  Question 
Find EOQ in Rs from the following data :-Annual consumption = 20, 000 units, Ordering and receiving cost of material = Rs 20 per order, Annual carrying cost or storage cost = 10% of unit cost of material, Cost of material = Rs 50.
  Correct Answer 
20000
  Your Answer 
10000
 Multiple Choice Single Answer
  Question 
Spares without which the system will not work are categorized as :-
  Correct Answer 
Vital
  Your Answer 
Vital
 Match The Following
Question
Correct Answer
Your Answer
Order quantity
Factor influencing process planning
Factor influencing process planning
Machine capacity chart
Dimensional accuracy
Special purpose machines
Mass production
Special purpose machines
General purpose machines with special toolings
Standard elemental time data
Compare alternative processes
Break even analysis
 True/False
  Question 
C type items would never be vital under VED analysis.
  Correct Answer 
False
  Your Answer 
False
 True/False
  Question 
In replenishment system, the type of ordering is either according to "stock level" or "pre-fixed time scale".
  Correct Answer 
True
  Your Answer 
True
 Multiple Choice Multiple Answer
  Question 
At company's subsidiary stores /tool crib following tools are stored :-
  Correct Answer 
Consumable tools , Inspection fixtures , Instruments and gauges
  Your Answer 
Consumable tools , Inspection fixtures , Instruments and gauges
 True/False
  Question 
Exponential smoothening is weighted average method.
  Correct Answer 
True
  Your Answer 
True
 Select The Blank
  Question 
The administrative lead time e.g. time involved in processing the order, which may be in periodical review system including the period until next review is called ________ lead time.
  Correct Answer 
Internal
  Your Answer 
Cumulative
 Select The Blank
  Question 
Heuristics methods involve drawing procedure diagram which indicates the ________ available for transferring tasks laterally from one column to another to arrive at most promising balance.
  Correct Answer 
Flexibility
  Your Answer 
Flexibility
 Multiple Choice Single Answer
  Question 
The light engineering company has one special purpose facing & centering machine And one copying lathe. The foreman has five work orders for processing . The operation Sequence is fixed [ each job is first faced and centered and then copy turned ] . The standard Hours required for each machine to process each work order are shown in the following Table :- Work Order Processing Time [Hours ] Facing & centering machine Copying Lathe I 16 40 II 30 60 III 20 6 IV 15 16 V 25 12 find sequence to minimize requirements of machine hours.
  Correct Answer 
IV-I-II-V-III
  Your Answer 
II-III-IV-I-V
 True/False
  Question 
In PERT, use of dummy activities is not much essential.
  Correct Answer 
False
  Your Answer 
True
 True/False
  Question 
The make-or-buy decision is not taken only at starting of a factory but has to be reviewed continuously.
  Correct Answer 
True
  Your Answer 
True
 Select The Blank
  Question 
Only satisfied customers get in ________ from new customers.
  Correct Answer 
Business
  Your Answer 
Business
 Multiple Choice Multiple Answer
  Question 
The following are salient features of the fixed order quantity system :-
  Correct Answer 
Reorder quantity is always the same which is usually economic order quantity , The time interval between deliveries varies. , Replenishment action is initiated when the stock on hand is just sufficient to meet demand during the lead time.
  Your Answer 
Reorder quantity is always the same which is usually economic order quantity , Replenishment action is initiated when the stock on hand is just sufficient to meet demand during the lead time. , Percent cumulative cost of item is taken into consideration.
 Match The Following
Question
Correct Answer
Your Answer
Tool order
To instruct tool crib to keep tools ready
Instruct to issue tools
Move order
Movement of material from stores to first machine
Movement of material from stores to first machine
Stores issue order
Instruction to stores to issue material
Instruction to stores to issue material
Inspection order
Report inspection results
Report inspection results
 Multiple Choice Single Answer
  Question 
Responsibility of smooth flow of work through different work centers or departments of company rests with :-
  Correct Answer 
Production control department
  Your Answer 
Production control department
 Select The Blank
  Question 
________ is the sum of set up time and run time.
  Correct Answer 
Manufacturing time
  Your Answer 
Manufacturing time
 Multiple Choice Single Answer
  Question 
Detachable ticket, after filling in required information is :-
  Correct Answer 
Placed in a tray/box
  Your Answer 
Given to progress section
 Multiple Choice Multiple Answer
  Question 
Subsidiary orders include :-
  Correct Answer 
Material Order , Shop order , Inspection order
  Your Answer 
Material Order , Shop order , Inspection order
 Multiple Choice Single Answer
  Question 
Long termed forecasts are for the period of :-
  Correct Answer 
5 to 10 years
  Your Answer 
One year
 Multiple Choice Multiple Answer
  Question 
If actual demand far exceeds forecast, it will result into :-
  Correct Answer 
Better utilization of equipment , Project margin , Higher material purchase
  Your Answer 
Better utilization of equipment , Higher material purchase , Increase in labour productivity
 Select The Blank
  Question 
Classification of items on basis of their capital lock up is called ________ analysis.
  Correct Answer 
XYZ
  Your Answer 
VED
 Multiple Choice Single Answer
  Question 
Physical Count method of collecting information from manufacturing shops is applicable in following situation :-
  Correct Answer 
Workshops employing few machines
  Your Answer 
Workshops producing small parts in huge quantities
 Multiple Choice Multiple Answer
  Question 
The expected time can be minimised by minimising following parameters :-
  Correct Answer 
Optimistic time , Pessimistic time , Most likely time
  Your Answer 
Pessimistic time , Lead time
 Multiple Choice Single Answer
  Question 
In order to maintain precedence relationships, the most common approach is to make use of :-
  Correct Answer 
Precedence diagrams
  Your Answer 
Precedence diagrams
 True/False
  Question 
There are five manufacturing systems. However, many manufacturers combines two or more systems to produce a final product.
  Correct Answer 
True
  Your Answer 
True
 Multiple Choice Multiple Answer
  Question 
HML Analysis helps to :-
  Correct Answer 
Access storage & security requirements , Keep control over departmental head level , Determine frequency of stock verification
  Your Answer 
Access storage & security requirements , Determine frequency of stock verification , Controls carrying cost
 Multiple Choice Single Answer
  Question 
The sourcing of vendors in case of 'B' type of items is :-
  Correct Answer 
Medium
  Your Answer 
Minimum
 Select The Blank
  Question 
Production Planning and Control department acts as a link between company's sales and ________ department.
  Correct Answer 
Manufacturing
  Your Answer 
Manufacturing
 Multiple Choice Multiple Answer
  Question 
Move orders, released for material movement from stores to first work center are used for following types of organizations :-
  Correct Answer 
Big steel plants , Power plants , Heavy machinery manufacturers
  Your Answer 
Big steel plants , Heavy machinery manufacturers , High volume white goods manufacturers
 Multiple Choice Multiple Answer
  Question 
Smoothing performs following activities:-
  Correct Answer 
Reallocation of resources , Improving utilization of resources , Conducting Heuristic approach
  Your Answer 
Improving utilization of resources , Conducting Heuristic approach , Conducting Load flow analysis
 Select The Blank
  Question 
________ phase of PPC makes sure that the programmed production is constantly maintained.
  Correct Answer 
Control
  Your Answer 
Control
 Multiple Choice Multiple Answer
  Question 
Process Sheet contains following information :-
  Correct Answer 
Material Specification , Sequence of operation , Skill of Labour
  Your Answer 
Material Specification , Sequence of operation , Order Quantity
 True/False
  Question 
The make-or-buy decision becomes necessary when the current source of supply is not able to supply the material in accordance with buyer's quality requirements.
  Correct Answer 
True
  Your Answer 
True
 Multiple Choice Single Answer
  Question 
Negative value of critical ratio :-
  Correct Answer 
Is meaningless
  Your Answer 
Indicates shortfall in scheduled delivery period
 Multiple Choice Multiple Answer
  Question 
In linear programming method of line balancing, there are three types of constraints namely :-
  Correct Answer 
Cycle time constraint , Step or task constraint , Precedence constraints
  Your Answer 
Cycle time constraint , Step or task constraint , Precedence constraints
 Multiple Choice Single Answer
  Question 
Let us suppose that activity M & N can not start until activity K & L are completed. Activities K &L are therefore :-
  Correct Answer 
Preceding
  Your Answer 
Preceding
 True/False
  Question 
XYZ analysis helps to identify few items which account for large amount of money locked up in the stock and take steps for liquidation / reduction.
  Correct Answer 
True
  Your Answer 
False
 True/False
  Question 
Overlapping of operations helps in compressing manufacturing time.
  Correct Answer 
True
  Your Answer 
False